JACoW logo

Journals of Accelerator Conferences Website (JACoW)

JACoW is a publisher in Geneva, Switzerland that publishes the proceedings of accelerator conferences held around the world by an international collaboration of editors.


RIS citation export for TUPDP081: The ESS Fast Beam Interlock System - Design, Deployment and Commissioning of the Normal Conducting Linac

TY  - CONF
AU  - Pavinato, S.
AU  - Carroll, M.
AU  - Gabourin, S.
AU  - Gorzawski, A.A.
AU  - Nordt, A.
ED  - Schaa, Volker RW
ED  - Götz, Andy
ED  - Venter, Johan
ED  - White, Karen
ED  - Robichon, Marie
ED  - Rowland, Vivienne
TI  - The ESS Fast Beam Interlock System - Design, Deployment and Commissioning of the Normal Conducting Linac
J2  - Proc. of ICALEPCS2023, Cape Town, South Africa, 09-13 October 2023
CY  - Cape Town, South Africa
T2  - International Conference on Accelerator and Large Experimental Physics Control Systems
T3  - 19
LA  - english
AB  - The European Spallation Source (ESS) is a research facility based in Lund, Sweden. Its linac will have an high peak current of 62.5 mA and long pulse length of 2.86 ms with a repetition rate of 14 Hz. The Fast Beam Interlock System (FBIS), as core system of the Beam Interlock System at ESS, is a critical system for ensuring the safe and reliable operation of the ESS machine. It is a modular and distributed system. FBIS will collect data from all relevant accelerator and target systems through ~300 direct inputs and decides whether beam operation can start or must stop. The FBIS operates at high data speed and requires low-latency decision-making capability to avoid introducing delays and to ensure the protection of the accelerator. This is achieved through two main hardware blocks equipped with FPGA based boards: a mTCA ’Decision Logic Node’ (DLN), executing the protection logic and realizing interfaces to Higher-Level Safety, Timing and EPICS Control Systems. The second block, a cPCI form-factor ’Signal Condition Unit’ (SCU), implements the interface between FBIS inputs/outputs and DLNs. In this paper we present the implementation of the FBIS control system, the integration of different hardware and software components and a summary on its performance during the latest beam commissioning phase to DTL4 Faraday Cup in 2023. 
PB  - JACoW Publishing
CP  - Geneva, Switzerland
SP  - 704
EP  - 708
KW  - MMI
KW  - controls
KW  - operation
KW  - software
KW  - FPGA
DA  - 2024/02
PY  - 2024
SN  - 2226-0358
SN  - 978-3-95450-238-7
DO  - doi:10.18429/JACoW-ICALEPCS2023-TUPDP081
UR  - https://jacow.org/icalepcs2023/papers/tupdp081.pdf
ER  -